Answer:
cost of goods manufactured= $81,204
Step-by-step explanation:
Giving the following information:
Cost of direct materials used in production $18,573
Direct labor 23,083
Factory overhead 33,632
Work in process inventory, March 1 24,104
Work in process inventory, March 31 18,188
To calculate the cost of goods manufactured, we need to use the following formula:
cost of goods manufactured= beginning WIP + direct materials + direct labor + allocated manufacturing overhead - Ending WIP
cost of goods manufactured= 24,104 + 18,573 + 23,083 + 33,632 - 18,188
cost of goods manufactured= $81,204