129k views
1 vote
Culler Construction Company agreed with the City of Orange Key to build a road. The project was to begin on December 1. One week after the work began, a hurricane struck the site, washing away so much land that the construction would be twice as expensive. As a result, Culler refused to continue the job, unless Orange Key paid a large sum in addition to the initial contract price. A promise by Orange Key to pay more than the original price is:_______

User Steven Yue
by
4.5k points

1 Answer

7 votes

Answer: D. Enforceable because Culler encountered unforeseen difficulties.

Step-by-step explanation:

Contractual obligations can be changed if one or both parties encounter unforeseen circumstances that would significantly alter their ability to fulfil their part of the contract.

In this scenario, Culler Construction would incur a significantly higher cost to carry out their side of the contract than what was agreed. The contract can therefore be changed and this change would be enforceable by law. The higher offer by Orange Key is therefore legal and enforceable.

User Jamie Jackson
by
4.5k points