Answer: Assembly Department
Step-by-step explanation:
Missing part of question is attached below.
Cutting Department
Under the direct method, the Cutting Department is allocated $62,000 of the Janitorial cost and $126,750 of the Cafeteria cost for a total of:
= 62,000 + 126,750
= $188,750
Assembly department
Allocated $248,000 of the Janitorial cost and $42,450 of Cafeteria:
= 248,000 + 42,450
= $290,450
Assembly Department is therefore the department that is allocated the most support department costs under the direct method.