Answer: $1.3 million
Step-by-step explanation:
Based on the information given in the question, if this change delayed check clearing by 1 week, then the annual savings that were realized will be:
= Weekly payroll × Cost of short term funds
= $10 million × 13%
= $10 million × 0.13
= $1.3 million
Annual savings realized is $1.3 million.