Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:

Hours
Wait time 30.2
Process time 0.4
Inspection time 0.2
Move time 3.6
Queue time 8.7
The delivery cycle time was:__________.
a. 3.6 Hours
b. 12.3 Hours
c. 42.5 Hours
d. 43.1 Hours

1 Answer

6 votes

Answer:

d. 43.1 Hours

Step-by-step explanation:

Calculation to determine what The delivery cycle time was

Using this formula

Delivery cycle time = Wait time + Process time + Inspection time + Move time + Queue time

Let plug in the formula

Delivery cycle time= 30.2 + 0.4 + 0.2+ 3.6 + 8.7

Delivery cycle time= 43.1 Hours

Therefore The delivery cycle time was:43.1 Hours