Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 24.9 Process time 2.6 Inspection time 0.5 Move time 2.2 Queue time 11.5 The throughput time was:

1 Answer

5 votes

Answer: 16.8 hours

Step-by-step explanation:

The throughput time will be calculated thus:

Inspection time = 0.5

Add: Process time = 2.6

Add: Move time = 2.2

Add: Queue time = 11.5

Throughput time = 16.8 hours

Therefore, the throughput time will be 16.8 hours.