If 4 labourers can finish a job in 6days how long would it take 3men to do the job


2 Answers

3 votes

Answer:

8 days

Explanation:

no of men no of days

4 6

3 let be x

there is indirect variation

4/3=6/x

since it is in indirect variation do the reciprocal of any one fraction among these two fractions

4/3=x/6

do cross multiplicatin

3*x=6*4

x=24/3

x=8

therefore it take 8 days to complete the same work by 3 men.