160k views
3 votes
Forte Co., had 5,900 units of work in process on April 1 that were 70% complete. During April, 18,000 units were started and as of April 30, 5,400 units that were 40% complete remained in production. How many units were completed during April

User Alan Han
by
8.6k points

1 Answer

4 votes

Answer:

18,500 units

Step-by-step explanation:

We simply use the physical units to determine the units completed

Units completed = Units in opening inventory + units started - units in ending inventory

therefore,

Units completed = 5,900 + 18,000 - 5,400 = 18,500

therefore,

Units completed during April amount to 18,500

User Oliver Blue
by
9.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.