232k views
1 vote
A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time

User Jakko
by
6.5k points

1 Answer

5 votes

Answer:

9

Step-by-step explanation:

Given that

There is five stations who have the process time of 5,9,4,9 and 8

We need to find out the bottleneck time

so, as we know that the bottleneck is the duration of the activity who have longer time

So as per the given situation the 9 has the longest duration activity time

So, the same is to be considered

User Iurii Dziuban
by
6.2k points