Answer: $21 per direct labor hour.
Step-by-step explanation:
Based on the information given in the question, the predetermined overhead rate that is used will be calculated as:
= Manufacturing overhead / Direct labor
where,
Manufacturing overhead = 5460
Direct labor = 3900/15 = 260 hours
Therefore, predetermined overhead rate:
= 5460/260
= $21 per direct labor hour.