Answer:
Results are below.
Step-by-step explanation:
To calculate the variable and fixed cost, we need to use the following formulas:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (370 - 122) / (840 - 220)
Variable cost per unit= $0.4
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 370 - (0.4*840)
Fixed costs= $34
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 122 - (0.4*220)
Fixed costs= $34
Total cost= 34 + 0.4x
x= machine hour
Now, the number of hours is 750:
Total cost= 34 + 0.4*750
Total cost= $334