Answer: 13.5 minutes
Step-by-step explanation:
Information turnaround time = Cycle time * Number of stations after error is made.
The most error-prone operation is step 2 so assuming an error happens there, there will be 9 more stations in the line.
Information turnaround time will therefore be:
= 1.50 * 9
= 13.5 minutes