7 men can complete a work in 52 days. In how many days will 13 men
finish the same work?

User Mina HE
by
3.5k points

1 Answer

6 votes

Answer:

if 7 men complete the work in 52 days, it means a man will take (52×7=364)days to complete the same piece of work. therefore 13 men will take (364÷13)days which is equal to 28 days.