Total materials variance is computed as
= [(AQ × AP) - (AQ × SP)]
AQ = Actual Quantity = 6,000
AP = Actual Price = $2.2
SP = Standard Price = $2
Then,
Rossi's inc. Materials price variance
= [(6,000 × $2.2) - (6,000 × $2)]
= $13,200 - $12,000
= $1,200 Unfavorable