Answer:
11.86%
Step-by-step explanation:
Project's discount rate = Rf rate + Beta*risk premium
Project's discount rate = 4.5% + 0.82*6.9%
Project's discount rate = 4.5% + 5.658%
Project's discount rate = 10.158%
Required rate = Project's discount rate + Adjustment rate
Required rate = 10.158% + 1.7%
Required rate = 11.86%
Thus, the firm set 11.86% as the required rate of return for the project.