Answer:
See below
Step-by-step explanation:
The above information is incomplete. Concluding part from similar question is seen below.
Direct labor $16,000
Factory overhead $12,800
To finished goods ($48,000)
Therefore, the amount of direct materials charged to job is computed as;
= Balance + Direct materials + Direct labor + Factory overhead - Finished goods
= $4,300 + $26,400 + $16,000 + $12,800 - $48,000
= $11,500
The next step is to deduct the job Still in work in process charged with direct labor.
= $11,500 - $2,300
= $9,200
Hence, the amount of direct materials charged to job no 5 is $9,200