Answer:
Overhead rate per unit= $124
Step-by-step explanation:
Giving the following information:
Budgeted output units 40,000 units
Budgeted machine-hours 10,000 hours
Budgeted variable manufacturing overhead costs for 40,000 units $310,000
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 310,000 / 10,000
Predetermined manufacturing overhead rate= $31 per machine hour
Now, for each unit:
Machine hours per unit= 40,000/10,000= 4
Overhead rate per unit= 31*4
Overhead rate per unit= $124