Answer:
$8,500 favorable
Step-by-step explanation:
The computation of the fixed overhead spending variance is shown below
= Budgeted fixed overhead - actual fixed overhead
= $184,800 - $176,300
= $8,500 favorable
We simply deduct the actual fixed overhead from the budgeted one so that the fixed overhead spending variance could come