Answer: Check attachment
Step-by-step explanation:
Quality cost:
Prevention $265000
Appraisal $175000
Internal failure $20000
External failure $40000
Total $500000
Percent of total quality was calculated as:
Quality cost classification/Total
e.g. Prevention = 265000/500000 × 100 = 53.00%
Check attachment for further information.