Answer: $8820
Step-by-step explanation:
The total amount of budgeted direct labor for March will be calculated thus:
Production in March = 980
Estimated labor hour = 0.5hour
Labor rate per hour = $18
Total amount of budgeted labor hour will be:
= 980 × 0.5 × $18
= $8820