Which stage in project management involves team members working on the assigned tasks as described in the project plan?

A.
initiation
B.
monitoring
C.
execution
D.
closure
E.
planning

User Windyjonas
by
4.8k points

1 Answer

4 votes

Answer:

C. execution

Step-by-step explanation:

  • The execution stage is 3rd stage in project management lifecycle is usually is longest phase as during which the teams develops the product or services and presents the final end product to the clients. Here the team members work on the same set of guidelines that are assigned or designed in a project.