Answer:
c. $59,400
Step-by-step explanation:
Complete word "All materials are added at the beginning of the process. For the month of June, direct labor was $49,500 and factory overhead was $9,900. The total conversion costs for the period is?"
Conversion Cost = Direct Labor + Factory Overhead
Conversion Cost = $49,500 + $9,900
Conversion Cost = $59,400