Answer:
$5,600,000
Step-by-step explanation:
The calculation of the Revenue that should Robertson recognize in 2017 is calculated below:-
For 2016
Estimated total cost = Cumulative cost incurred + Est. additional cost to complete
= $3,000,000 + $6,000,000
= $9,000,000
Percentage of completion = Cumulative cost incurred / Estimated total cost
= $3,000,000 / $9,000,000
= 33.33%
Contract price = $12,000,000 * 33.33%
= $4,000,000
So, revenue for 2016 = $4,000,000
Now for 2017
Estimated total cost = Cumulative cost incurred + Est. additional cost to complete
= ($3,000,000 + $5,000,000) + $2,000,000
= $10,000,000
Percentage of completion = Cumulative cost incurred / Estimated total cost
= $8,000,000 / $10,000,000
= 80%
Contract price = $12,000,000 * 80%
= $9,600,000
Revenue = $9,600,000 - $4,000,000
= $5,600,000