Which section chief is required to develop an incident action plan for large events? Operations Logistics Finance Planning

1 Answer

3 votes

Answer:

Planning

Step-by-step explanation:

The Planning section chief is needed to develop and organize an incident action plan for the large events. He is one responsible for preparing the incident action plans. He also manages the information as well as maintains the situational awareness for the incident to take place.

He is in control of the overall execution of the event.