Answer:
See below
Explanation:
We can make a the number of days and y the number of workers
Since we were told there is an inverse relationship between the days required to build the house and the number of workers required, then,
The equation would be
y = k/x
Here, y is inversely proportional to x and k is the constant proportionality
So, out required equation would be
a = k/n
Fixing the values, we'll have
55 = k/8
k = 55 × 8
k = 440
The number of days required to build a similar house with 5 workers will now be
= 440/5
= 88 days