Compute the Work-in-Process transferred to the finished goods warehouse on April 30 using the following information:

Work-In-Process Inventory, April 30 $175
Direct material purchased during April 150
Work-In-Process Inventory, April 1 200
Direct labor costs incurred 300
Manufacturing overhead costs 250
Direct materials used in production 125

a. $1,170.
b. $1,035.
c. $1,120.
d. $985

User Baumgarb
by
8.2k points

1 Answer

2 votes

Answer:

$700

Step-by-step explanation:

The computation of work-in-progress transferred to the finished goods is given below:

We know that

= Work-In-Process inventory, April 1 + Direct materials used in production + Direct labor costs incurred + Manufacturing overhead costs - Work-In-Process Inventory, April 30

= $200 + $125 + $300 + $250 - $175

= $700

Hence, this is a correct answer

User Rzetterberg
by
8.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories