A project manager is trying to convince management to use more formal project management procedures and has decided to start improving the company's project management by obtaining a project charter for each of his projects. Which of the following best describes how a project charter would help the project manager?

a. It describes the details of what needs to be done
b. It lists the names of all team members
c. It gives the project manager authority
d. It describes the project's history

User DragonBobZ
by
4.2k points

1 Answer

3 votes

Answer: C. It gives the project manager authority.

Step-by-step explanation:

A project charter is referred to as a formal document that describes what a project will be about. It shows the project objectives, how it will be done, the stakeholders etc

The project charter is used to formally outline a project and authorize it in an organization. It covers the scope of the project, budget, risks involved etc.

Therefore, the correct option is C