Answer:
62.4kanbans
Step-by-step explanation:
Calculation to determine How many kanbans do you need for this connector
First step is to calculate the Demand During Lead Time
Using this formula
Demand During Lead Time= 2 days x Daily Demand
Let plug in the formula
Demand During Lead Time=2*600
Demand During Lead Time=1,200
Second step is to calculate the Safety Stock
Using this formula
Safety Stock= 50 days of Production x Daily Demand
Let plug in the formula
Safety Stock=50*600
Safety Stock=30,000
Third step is to calculate the Lot Size using this formula
Lot Size= Demand During Lead Time + Safety Stock
Let plug in the formula for
Lot Size=1200+30,000
Lot Size=31200
Now let calculate How many kanbans do you need for this connector. Using this formula
Numbers of kanbans =Demand During Lead Time + Safety Stock / Size of Container
Let plug in the formula
Numbers of kanbans=31200/500
Numbers of kanbans=62.4kanbans
Therefore How many kanbans do you need for this connector is 62.4