Answer:
c. 48,100.
Step-by-step explanation:
The computation of the actual labor hours worked is shown below;
Actual Overhead $392,000.00
Less: Underapplied overhead $7,200.00
Applied Overhead ($392,000 - $,7200) $384,800.00
Predetermined overhead rate $8.00
Actual labor hours ($384,800 รท 8) $48,100
hence, the actual labor hours worked is $48,100
Therefore the option c is correct