Your manufacturing requires parts to go sequentially through process A, B, and C. A machine can do process A in 1
minute, B in 2 minutes, and C in 3 minutes. You have two A machines, one B machine, and three C machines. Which process is the
bottleneck (can produce the fewest items per unit time)?