Answer:
Jumpst Corporation
Maintenance cost expected to be incurred during August is:
= $19,600
Step-by-step explanation:
a) Data and Calculations:
Cost formula Y = $5,200 + $0.40X
where X = machine-hours
Y = Expected maintenance cost
August budgeted machine hours = 36,000
Therefore, Y = $5,200 + ($0.40 * 36,000)
= $5,200 + $14,400
= $19,600
b) From the cost formula, one can summarize that the $5,200 is a fixed cost while the $0.40X is the variable cost element. Together, these two elements make up the total cost for the Maintenance cost for any month, where X represents the value of machine hours expected to be used in the month.