Answer:
$2,420
Step-by-step explanation:
Calculation to determine what The materials and supplies in the flexible budget for November would be closest to:
Using this formula
Cost = Fixed cost + (Variable cost per unit × q)
Let plug in the formula
Cost= $1,910 + $10 × 51
Cost= $2,420
Therefore The materials and supplies in the flexible budget for November would be closest to:$2,420