Answer:
Upper Control Limit for a c-chart = 9.1
Explanation:
Given - construction company has just constructed 150 new apartments. An external inspector is hired to do the final checking before they are given way to prospective customers. Inspector at random selects 8 apartments and and counts how many defects are in each one them. He finds 7,3, 2, 1, 2, 5, 4, 4 defects.
To find - What will be Upper Control Limit for a C chart ?
Proof -
Upper Control Limit for a c-chart = c bar + 3(square root of c bar)
Now,
c bar =
= 3.5
∴ we get
Upper Control Limit for a c-chart = 3.5 + 3(square root of 3.5)
= 3.5 + (1.87)
= 3.5 + 5.61
= 9.1
⇒Upper Control Limit for a c-chart = 9.1