Answer:
Under the activity-based costing system, the total cost of "unused capacity" related to the assembly activity for the most recent year is closest to:
$17,727.27.
Step-by-step explanation:
a) Data and Calculations:
Activity cost pool Total cost Practical capacity ABC rates
of activity
Assembly $65,000 55,000 machine hours $1.182 /mh
Processing $76,000 2,500 orders $30.40 / order
Inspection $55,000 2,200 inspections $25.00 / inspection
Product X
Number of units made = 40
Machine hours required = 690
Processing orders = 40 orders
Inspection hours = 10 hours
Direct material cost per unit = $45
Direct labor cost per unit = 35
Most recent actual machine hours = 40,000 hours
Unused capacity = 15,000 (55,000 - 40,000)
Total cost of unused capacity = $17,730 (15,000 * $1.182) approx.