Answer:
Results are below.
Step-by-step explanation:
We weren't provided with the number of hours per unit or the hourly rate. But, let's suppose that each unit requires 0.1 hours and the hourly rate is $10.
Production= 28,000 units
Direct labor hours required= 28,000*0.1= 2,800 hours
Total direct labor cost= 2,800*10= $28,000