Project A = 4 years 4 months
Project B = 2 years 6 months
Step-by-step explanation:
The payback period of a project is the length of time it takes for the cash flows to equal the amount of initial investment.
Project A ( $150,000) = $ 45,000 + $ 45,000 + $ 45,000 + $15,000 / $ 45,000 x 12
= 4 years 4 months
Project A ( $150,000) = $ 75,000 + $ 60,000 + $15,000 / $ 30,000 x 12
= 2 years 6 months