Problem: It takes 1200 workers 8 years to build 3 ziggurats. How many years would It take 1600 workers to build 25 ziggurats?
asked
May 8, 2022
115k
views
4
votes
Problem: It takes 1200 workers 8 years to build 3 ziggurats. How many years would It take 1600 workers to build 25 ziggurats?
Mathematics
college
Chhay Rith Hy
asked
by
Chhay Rith Hy
7.4k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
2
votes
Answer:
50 years
Explanation:
trust me.
Moses Lee
answered
May 13, 2022
by
Moses Lee
7.6k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.6m
questions
11.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org