At the Charming Chair Factory, they make 20 chairs

per day when 5 workers are on duty. If they need to
make ioo chairs in one day, what equation should
they use to figure out how many workers to schedule?

1 Answer

4 votes

Answer:

100÷(20÷5)

Explanation:

first find out how many chairs each worker made

20÷5=4

then divide 100 by 4 and that will give you 25

they would need 25 workers the equation that they should use is

100÷(20÷5)