A factory that makes computer monitors produced 247 monitors during 5 working days. Which is closest to the number of working days that should be allowed to fill an order for 1,000 monitors?

User Ardila
by
8.6k points

1 Answer

4 votes

Answer:20 days

Step-by-step explanation:247/5=49.4

That’s the amount they monitor per day 49.4

Then they wanted to monitor 1000

So 1000/49.4=20.24(estimate)

20 days is the answer

I’m not 100% sure it might be 21 because it will take 21 days to monitor at LEAST 1000

User Jramirez
by
8.8k points