218,802 views
19 votes
19 votes
Select the correct answer.

Thomas, a senior manager at a manufacturing firm, is coming up with ideas for a new product. Thomas has made a list of the following tasks that form a part of this project, along with their respective durations.

Create questionnaires to interview potential customers (7 days)
Find existing information about the market from online sources and trade journals (6 days)
Interview the respondents with the help of the questionnaire (10 days)
Design a new product according to the information obtained through the interviews (30 days)
If Thomas conducts a Critical Path Analysis to schedule these activities, what is the most likely duration that the activities will take to be completed?
A.
50 days
B.
40 days
C.
57 days
D.
47 days
E.
67 days

User Zufar Muhamadeev
by
3.3k points

1 Answer

24 votes
24 votes

Answer: I believe it is "C" 57 days.

Step-by-step explanation: Add all the dates together and round to the nearest number of days.

User Johannes Wiesner
by
2.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.