647 views
2 votes
Select the correct answer.

Mike needs to write the primary objectives of a project in a project plan. In which section should he write them?
A.
scope
B.
overview
c.
baselines
D.
schedule

User Zhenya
by
4.6k points

1 Answer

1 vote

Answer:

overviews

Step-by-step explanation:

User Itro
by
5.0k points