Answer:
the work in process should be debited for $13,520 and factory overhead should be credited for $96,000
Step-by-step explanation:
The computation is shown below;
Work in process is
= $96,000 ÷ 12,000 × 1,690
= $13,520
So here the work in process should be debited for $13,520 and factory overhead should be credited for $96,000
Therefore the same would be considered and relevant
The same is fit to the given situation