Answer:
2,421.89
Step-by-step explanation:
Reorder point = Daily demand*Lead time + Z*STANDARD DEVIATION *√(Lead time)
Reorder point = 300*8 + 1.65*4*√11
Reorder point = 2,400 + 21.8897
Reorder point = 2,421.8897
Reorder point = 2,421.89
So, the reorder point for a 95% service level is 2,421.89.