The I-75 Carpet discount store has annual demand of 85,700 yards for Super Resistant carpet. The annual carrying cost for a yard of this carpet is $2.25 per yard and the ordering cost is $350. The store is open 52 weeks per year. Assume that the expected value of daily demand is 200, that the standard deviation for daily demand is 4 and that the lead time to fill an order is 11 days. Assume that the EOQ is 5164 yards. What would be the reorder point for a 95% service level?

User Garvin
by
8.1k points

1 Answer

4 votes

Answer:

2,421.89

Step-by-step explanation:

Reorder point = Daily demand*Lead time + Z*STANDARD DEVIATION *√(Lead time)

Reorder point = 300*8 + 1.65*4*√11

Reorder point = 2,400 + 21.8897

Reorder point = 2,421.8897

Reorder point = 2,421.89

So, the reorder point for a 95% service level is 2,421.89.

User Ganjeii
by
8.4k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories