A rice farmer employs 15 men to harvest his crop. The men take 12 days to do the job. If he had employed 9 men, how many days would it have taken them?



User Novy
by
5.0k points

1 Answer

4 votes

Answer:

15 men * 12 days = 180 man-days

180 man-days / 9 men = 20 days

From a project management stand point man-days doesn’t really equate to much so while you can evaluate schedule, you would typically desire to see more information than this.