Answer:
Variable cost per unit= $2.28
Step-by-step explanation:
Giving the following information:
January 940 $ 5,490
February 1,840 $ 6,980
March 2,480 $ 8,100
April 640 $ 3,900
To calculate the variable cost per machine hour under the high-low method, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (8,100 - 3,900) / (2,480 - 640)
Variable cost per unit= $2.28