25.5k views
5 votes
You work on a concrete crew starting a construction project. once the pouring begins, it must continue nonstop until it is completed. your crew will work an 8-hour shift along with two other crews. The total project requires 175,000 yards of concrete. your supervisor estimates that each crew will pour around 1200 yards per hour. how many consecutive days should you plan to work on this project?

A. 3
B. 6
C. 18
D. 27
E. 146

ACT WORKKEYS 2022

1 Answer

9 votes

Answer:

look at the workey??

Explanation:

User Dezzie
by
5.6k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.