Answer:
d.$72 per machine hour
Step-by-step explanation:
Predetermined overhead rate = Budgeted Overheads ÷ Budgeted Activity
therefore,
Predetermined overhead rate = $11,742,000 ÷ 164,000
= $71.598 or $72
The predetermined overhead rate based on machine hours is $72 per machine hour.