Answer:
Total labor hour = Units*Operating hours
Labor cost= Total labor hours * Hourly wage rate
QUARTER
1 2 3 4
Units 20,330 35,270 25,370 30,390
DLH time per unit 1.70 1.70 1.70 1.70
Total labour hours need 34561 43129 59959 51663
Hourly wage rate 17 17 19 19
Budgeted direct labor hour 587535 733193 1138221 981597