18. Working for 10 hours a day, a painter completes a job in 15 days. How long would it take him if he works for 6 hours a day? A. 20 days B. 25 days C. 30 days D. 40 days E. 90 days​

User FryHard
by
2.2k points

1 Answer

24 votes
24 votes

working: inverse proportional to time

10/6 x 15 = 25 days