55.5k views
3 votes
If 12 men complete a piece of work in 10 days in how many days would 15 men complete the same work​

User Vasart
by
4.2k points

2 Answers

3 votes

Explanation:

number of men =12

time taken = 10 days

time taken to complete the work by 15 men = 12÷10=1.2

= 1.2 ×15 = 18

therefore, 18 days is taken to complete the work by 15 men

User Jlh
by
4.2k points
7 votes
12 men = (1/10) work per day

15 men = (1/8) work per day

So 8 days
User JoergB
by
4.2k points